The Village of Fredonia has approved moving forward with the hiring of LaBella Associates as the engineers for the Water Improvement Project.

​

​

​​

​

​

​

​​​

​​

 

 

 

 

 

 

 

 

Overall Schedule​

​

LaBella phases.png

 

 

 

 

 

Ongoing Work:

  • Stakeholder Engagement

  • Data Collection

    • Topographical survey​

    • Geophysical survey

    • Geotechnical soil investigations

    • Environmental feature delineations

    • Water quality and blending study

  • Project planning & funding application development

  • Preliminary design & system hydraulic modeling

Questions and Comments?

If you have questions or would like to share input, please click the "Officials & Departments" link above and submit questions and/or input by email to either Mayor Ferguson or Trustee Wandel

​

Specific Updates and Reference Documents:

project funding labella 7.8.26.png

Starting on Wednesday, 5/27, the Village and LaBella Associates will be completing field investigations along Water St. and Webster Rd. The field work is non-destructive and aimed at documenting existing conditions. No action is needed, however if you have any questions or concerns, please contact Village Hall. 

Starting on Wednesday, 4/22, the Village and LaBella Associates will be completing geophysical field investigations along Water St. between its intersection with Webster Rd. and its intersection with Liberty St., and along Webster Rd. near the existing potable water storage tank. The field work is non-destructive and aimed at characterizing existing soils. No action is needed, however if you have any questions or concerns, please contact Village Hall. 

 

​